In addition to the common requirements for all applications (Article 4), the Ministerial Order sets out specific supporting documentation requirements for each mechanism:
a) Split: allocation of capacity among each resulting TRC and a declaration of the capacity to be made available for release.
b) Aggregation: identification of all TRCs to be aggregated, the intended interconnection point, a summary justification, identification of the future holder and, where the TRCs belong to different holders, an authorising document from each holder declaring their agreement to the aggregation.
c) Waiver: indication of the capacity subject to the waiver and identification of any overdue obligations or costs incurred.
d) Exchange: identification of the TRCs to be exchanged, a joint declaration by the holders, a description of the resulting configuration, indication of the intended injection capacity allocation for each resulting TRC, demonstrating that it does not exceed the aggregate total, and environmental documentation, where applicable.
e) Release and Allocation: identification of the TRC and the injection capacity to be made available for release, expressed in MVA (on the assignor’s side); indication of the code of the pending application included in DGEG’s list, the injection capacity value sought, identification of the interconnection point, characterisation of the primary energy sources and proof of the bond provided (on the applicant’s side).
f) Technology change: identification of the current and replacement technology, demonstrating maintenance of overall capacity.
g) Hybridization: identification of the complementary technology, capacity and operating period, and identification of the technology originally envisaged in the TRC; additional documentation for onshore installations (Order no. 11740-B/2021); grid charging capacity through the RESP where the complementary technology is storage.
h) Partial reduction: current and intended capacity, form of compensation (storage or other technology), with demonstration of compliance with the limits set out in DL 100/2026.
i) Change of interconnection point: identification of the current and intended point, characterisation of the connection grid and a declaration by the holder attesting to the absence of any other pending application for a change of interconnection point relating to the same TRC.